I managed client communication and requirements clarification, and completed approximately 90% of the Excel capacity calculator development. The model linked task times, staffing and mould cycles to help an industry partner compare output, costs and delivery times across manual and automation scenarios.
With one eight-hour shift per day, the model’s 10-tile manual configuration with 21 workers estimated 1,420 tiles per day, requiring 36 working days to meet its 50,000-tile target.